Subject category: Reporting
News feed for this listing: Syndicate content

Setting Permission to Generate Programme PDF Reports

Users with the appropriate permissions can run and customise i-lign Programme and Project PDF Reports on an ad hoc basis, but only users who have the Configure Templates permission can make them available in the Saved Report Templates shared list.

Setting Permissions to Access and Create Programme Reviews

To give users the ability to create and / or access Programme PDF Reports, an i-lign Administrator who has the permission to edit Organisation Security Roles needs to

Setting Permissions to Create PDF Report templates

Users with the appropriate permissions can run and customise i-lign Programme and Project PDF Reports on an ad hoc basis, but only users who have the Configure Templates permission can make them available in the Saved Report Templates shared list.

How is the Project Percentage Complete figure calculated?

The Project Percentage Complete figure displays on the Project Snapshot.

Creating Programme Reviews

A Programme Review allows Programme Managers to comment on the overall health of a programme of work, at the same time as Project Managers are providing a review of their individual projects.

Exporting Timesheets

Users with the appropriate permissions can export approved Timesheets to several accounting system formats.

Denormalised Reporting Tables

In addition to the standard live tables in the i-lign database, customers with inhouse installations of i-lign have access to summary tables.

Why are Tasks marked as 100% complete showing in an overdue Task list?

i-lign considers a Task to be complete when an actual end date is entered.