Topics from the 'Managers' category:
Importing Resources: Overview
The i-lign tool has the ability to import existing resource information. This feature is particularly useful in situations where multiple users need to be created in i-lign, for instance at implementation time, or adding another team to the i-lign user base. Last edited by Susan from i-lign on Tue, 2009-12-29 13:13.
Microsoft Project Import Procedure
Follow these steps to import a MS Project file into i-lign. (This option is only available in Microsoft Project 2002 or higher.) Last edited by Susan from i-lign on Tue, 2009-12-22 16:48.
Estimating Project Resource expenses
i-lign uses four types of estimate. All of them calculate projected expenses between the Start and End dates of the project. Last edited by Susan from i-lign on Mon, 2008-12-15 16:20.
Project Resource Planning
The Project Resource Planning consolidated view displays a list of planned project and resource information, from the current month and for the following eight months. Last edited by Elaine on Tue, 2007-08-21 13:16.
How is the Project Percentage Complete figure calculated?
The Project Percentage Complete figure displays on the Project Snapshot. Last edited by Elaine on Thu, 2007-08-09 10:50.
Setting Exchange Rates
Organisations spanning several countries will find the ability to display consolidated budgets in different currencies very useful. Last edited by Susan from i-lign on Wed, 2008-12-17 13:08.
Can an i-lign schedule be exported to Microsoft Project ?
The export will output the i-lign schedule data (tasks, milestones, constraints, and resource allocations) in an .xml format that can be read by MS Project 2002 and above. Last edited by Susan from i-lign on Wed, 2010-01-06 15:28.
Managing Project Number Allocation
Project number allocation can be centrally managed either externally to i-lign or by using i-lign's auto-number generation function. Last edited by Susan from i-lign on Mon, 2010-02-15 10:28.
Changing the Lifecycle of an Active Project
An active project may have approved Stages in its Lifecycle. Its it is not possible to delete or edit approved Stages. However, you can replace your existing Lifecycle with a new Lifecycle that takes into account that an approved stage needs to be extended, the stage was approved by mistake, or a decision has made to follow a different methodology. Last edited by Susan from i-lign on Tue, 2009-12-29 15:08.
Importing XML file problems
Schedules that are exported to XML and then re-imported without saving them in MS Project will not be imported correctly. Last edited by Susan from i-lign on Tue, 2009-12-22 16:50.
|
|||||||||||||||||||||||||||||||||||||||||||||||||