Topics from the 'Project Reports' category:How is the Project Percentage Complete figure calculated?
The Project Percentage Complete figure displays on the Project Snapshot. Last edited by Elaine on Thu, 2007-08-09 10:50.
Why are Tasks marked as 100% complete showing in an overdue Task list?
i-lign considers a Task to be complete when an actual end date is entered. Last edited by Susan from i-lign on Mon, 2010-02-15 10:39.
|