2 June 2009
Maintenance release containing mostly bug fixes for the Project Gantt chart
Minor Improvements
- [PW-4672] - Tasks that are constrained, or that constrain other tasks, cannot be made into summary tasks in the Project Gantt chart
- [PW-4679] - If an item cannot be indented or outdented in the Project Gantt chart then the tooltip on the popup menu explains why
Bugs fixed
- [PW-4632] - Internet Explorer 7 incorrectly says that pages that contain a timeline widget (ie Project Summary, Corporate, Event List) contain secure and insecure content when they are viewed over a secure connection
- [PW-4658] - Deleting a Task or Milestone in the Project Gantt chart, rearranging summary tasks and then saving may cause other Tasks and Milestones to be moved to new parents when the 'save' button is clicked
- [PW-4661] - Adding a new Resource to a Project fails with a system error if all available Resources are already assigned to the Project
- [PW-4665] - Saving a project in the Project Gantt chart occasionally fails with an error saying 'Input Set size differs from original size'
- [PW-4668] - The Event timeline and list views do not show more than one Event with the same name
- [PW-4669] - Tasks and Milestones cannot be outdented to the top level (introduced in 4.3.3)
- [PW-4671] - Merging in the Project Gantt chart fails when a constraint is added in the gantt and one of the constrained Tasks is deleted in the browser
- [PW-4673] - The Tasks with Action Items PDF Subreport sorts the action items alphabetically (inconsistent with the normal order of action items).
- [PW-4676] - Check box labels that should show Project status values are not shown when refreshing Project Roles from the defaults - IE6 only
- [PW-4677] - Finding a Resource by name using the autocomplete control fails with a system error when the user types in some characters, deletes them and then clicks the 'Go' button - IE6 only